Lvivskyi Kvartal RC: in the seventh stage, the laying of tiles on the balconies is almost complete

June 07, 2021

Real Estate Corporation RIEL reports that in the seventh stage of  Lvivskyi Kvartal RC, the laying of tiles on the balconies is being completed. This was announced by the construction manager.

At the same time, it is reported that the horizontal heating and ventilation and water and sewage networks on the -1 floor are 95% complete, the rest of the floors are 100% complete; the fire alarm system on the 1st floor is 97% complete, on the rest of the floors, it is 100% complete.

We would also like to provide the following information: the façade is 99% complete, and the improvement activities are in process.

Investors can familiarize themselves with the construction work schedule, photo reports, graphic materials and news from the construction site on the interactive portal of the seventh stage.

We will call you back, advise, select the best options
Phone number *
Thank you for your application! We will contact you shortly.
Subscribe to news and promotions
Thank you for subscribing to our newsletter!
Constructors

ЧП «ЖБК «РІЕЛ»

Join our social networks
Contact us in convenient way
(044) 499-98-86
Feedback
The exchange rate as of 11/21/2024 is 41.35 UAH.
Sales departments
Kyiv, str. Konovaltsya, 30
Kyiv, 56, Ukrainian Air Force avenue
© 2024  Lvivskyy Kvartal. All rights reserved.Privacy policy
Made in WEZOM
This site uses cookies for more comfortable work of the user. By continuing to browse the site, you agree to the use of cookies.